This development proposal was approved by the neighborhood and city council. It failed over a public funding dispute between the mayor's office and the developer.

This website was designed to promote neighborhood input for the development, which would have encompassed the entire 800 block of E.Washington Ave (north side), currently utilized for auto sales..

pic

A neighborhood committee worked with the developer to solicit public feedback.The committee consisted of
Alderperson Brenda Konkel and three representatives each from Tenney Lapham and Old Marketplace neighborhoods.

News:

August 8,2006
Developer informs the neighborhood that the project has been withdrawn.

March 25,2006 WSJ
New Gorman plan unveiled for East Wash

March 24, 2006, Mayor Cieslewicz
Work continues on Gorman project ,

March 6
Statements from Mayor Dave Cieslewicz and developer Gary Gorman that have recently circulated via email.
Statement from Downtown Madison, Inc.'s (DMI)

Local media articles:
Let Developer Kill Project , WSJ, opinion, March 11,2006
Cda Doesn't Vote On East Wash Plan , WSJ, March 10,2006
Don't Give Up On East Side Project , WSJ, opinion, March 10,2006
Editorial: Keep Gorman Project On The Table
, Channel 3, March 6,2006
Plan To Revive East Side Project Offered, WSJ, March 4,2006
Gorman Project Pullout Is A Loss, Cap. Times letters, March 4,2006
Development May Get Reboot, WSJ, March 3,2006
Konkel Tries To Revive Gorman Deal, Cap.Times, March 2, 2006
East Side Project Appears To Be Dead, WSJ, Feb. 28,2006
East Side Project Brought To A Halt, Cap. Times, Feb.28,2006


 

Neighborhood documents

Meeting schedule:

Links

 

800 block email discussion listserver -- Want to be on it? Send a request to the address below.

Contact: David Waugh,

Last updated August 16,2006